The primary outputs of the Plan-Procurement-Management process are the procureme...

✅ The verified answer to this question is available below. Our community-reviewed solutions help you understand the material better.

The primary outputs of the Plan-Procurement-Management process are the procurement management plan, procurement Strategy, bid documents, procurement statement of work, source selection criteria, make-or-buy decisions, and independent cost estimates.