Company X produces 2 products (A and B). Company X uses ABC costing and one of the activity cost pools is the assembly (with an overhead cost of $517723), which has as cost driver the number of total parts. Company X presented the following
Product A Product B
Units
produced 5000 10000
Number
of parts 20 30
What will be the overhead
costs per unit as it relates to the assembly cost pool for Product B?