Contractor A’s negative CECP in a bidding competition indicates that_____.
his competitor is able to produce a bid equal to his cost estimate.
he has a chance of winning.
his competitor is able to produce a bid lower than his cost estimate.
his cost estimate is higher than the lowest bid.