Consider the following workload :

  • Job A arrives at time 0s and runs for 6s
  • Job B arrives at time 1s and runs for 6s
  • Job C arrives at time 2s and runs for 3s

What is the average turnaround time (rounded to two decimal places) using the SJF scheduling policy?

❌
❌
✅
❌