A software development team is using the Waterfall model for a banking applicati...

✅ The verified answer to this question is available below. Our community-reviewed solutions help you understand the material better.

A software development team is using the Waterfall model for a banking application project. The requirements phase took 2 months, but during the design phase, the client requested major changes to the authentication system. What is the PRIMARY disadvantage the team will face?