A project's durationcan be reduced by:
A project's duration
can be reduced by:
Adding tasks to thecritical path
Adding tasks to the
critical path
Shortening the duration of critical path tasks
Completing thebackward pass first
Completing the
backward pass first
Adding shorter routesaround the critical path
Adding shorter routes
around the critical path