In a complex PERT network, Activity M takes 8 weeks to complete and connects Eve...

✅ The verified answer to this question is available below. Our community-reviewed solutions help you understand the material better.

In a complex PERT network, Activity M takes 8 weeks to complete and connects Event 4 to Event 5. Event 4 has an Early Time of 10 weeks and a Last Time of 12 weeks. Event 5 has an Early Time of 20 weeks and a Last Time of 20 weeks. If an unforeseen supply chain issue delays Activity M by exactly 3 weeks (making its duration 11 weeks), what is the direct consequence on the project?