Which of the following is not true about the concern of monitoring and controlling project work process?
Decreasing the number of change request in order to increase the efficiency of the project
Providing forecasts to update current cost and current schedule information
Monitoring implementation of approved changes as they occur
Comparing actual project performance against the project management plan