What does aplan-driven process entail?
What does a
plan-driven process entail?
The processactivities are spontaneously decided upon
The process
activities are spontaneously decided upon
All processactivities are planned in advance and progress is measured against this plan
All process
activities are planned in advance and progress is measured against this plan
None of the answer choices are correct
The planning isincremental and easily changes to accommodate customer requirements
The planning is
incremental and easily changes to accommodate customer requirements