What is latest start date (LSD) of activity E?
Explain what are time schedule, resource schedule and target schedule? (in about 120 words)
For the given overlapping network diagram:
(1) Describe the relationship between all activities. (For example, AC is Finish to Finish).
(2) Calculate the Early Start Date and Early Finish Date of each activity.
(3) Determine the project duration.
An overlapping network diagram is given below. What is the Early Finish Date of Activity E?
You have a project to be completed in 6 months. At the third month, project team members report that it is 45% complete. The planned budgeted cost at the third month was $250,000. You have spent $232,000 of the project's $500,000 budget. What is the PV, AC, BAC, EV, CV, CPI, SV, SPI, ETC and EAC at the day of reporting the project status?
Comment on the results and explain briefly what the value of each item means for the project.
( PV: Planned Value; AC: Actual Cost; BAC: Budget At Completion; EV: Earned Value; CV: Cost Variance; SV: Schedule Variance; CPI: Cost Performance Index; SPI: Schedule Performance Index; ETC: Estimate To Completion; EAC: Estimate At Completion )
All of the following statements are true EXCEPT: