The following precedence diagram shows all the activities involved in a housing project. For each activity, the most likely activity duration, the most optimistic and most pessimistic time have been given in the table (in weeks).
(1) Calculate the probability that the project can be completed in 29 weeks. Choose from answers (a, b, c, d)
(2) Calculate the probability that the project can be completed in 30 weeks. Choose from answers (e, f, g, h)
(3) If we want to be 98% sure that the project will be completed on time, how long we should schedule it? Choose from answers (i, j, k, l)
In PERT, the expected project duration is a sum of the mean duration of all _____ activities in a schedule.