During a meeting with some of the project stakeholders, the project manager is asked to add work to the project scope of work. The project manager had access to correspondence about the project before the charter was signed and remembers that the project sponsor specifically denied funding for the scope of work mentioned by these stakeholders. The BEST thing for the project manager to do would be to :to :