A manufacturer and a critical component supplier disagree about repeated engineering changes made after contract award. The supplier argues that the changes fall outside the original statement of work and require compensation. The buyer argues that the changes are normal refinements within the agreed design process. The relationship is important, the dispute is technically complex, and both firms want a business-level resolution before legal positions harden. Which mechanism is most appropriate to resolve this dispute?