Explain in what situation PERT analysis may underestimate schedule risk, and in what situation PERT can be more accurate in predicting schedule risk? (in about 100 words)
See below for a project's precedence diagram and each activity's duration given in the table.
(1) If the project manager for the following project wants to be at least 90% sure about the scheduled completion time, how many weeks the project should be scheduled?
(2) What is the possibility that the project will take longer than 33 weeks?
Decide which phoneme the letters se (like in loose) represent.
What is earliest finish date (EFD) of activity F?
What the earliest start of activity G for the following network diagram? (FF-5 means Finish to Finish with -5 days lead time.)
Briefly explain in what situation Line of Balance can be used? (in about 80 words)
Consider the network below. Activity durations are given in nodes.
What is total float of activity D?
What is resource leveling? What are the impacts of resource leveling on project schedule? (in about 150 words)
50 similar houses are to be built in a housing project. For each house, 9 trade activities need to be carried out, and their relationships are given in the following network diagram. The duration of each trade activity for one house is listed in the table.
Assume all the trade activities need to be carried out continuously and the total project needs to be finished in the shortest possible time.
(1) Calculate the total duration, staring week and finishing week for each trade.
(2) Determine the total project duration.