logo

Crowdly

Browser

Додати до Chrome

Questions Bank (1599262 total)

Explain in what situation PERT analysis may underestimate schedule risk, and in what situation PERT can be more accurate in predicting schedule risk? (in about 100 words)

Переглянути це питання

See below for a project's precedence diagram and each activity's duration given in the table. 

(1) If the project manager for the following project wants to be at least 90% sure about the scheduled completion time, how many weeks the project should be scheduled?

(2) What is the possibility that the project will take longer than 33 weeks?

Q8 2019 final exam BLDG2023

Переглянути це питання
Based on the following network diagram, what is the duration of the critical path? (FF+2 means Finish to Finish with 2 days lead time.)

0%
0%
0%
0%
Переглянути це питання

Decide which phoneme the letters se (like in loose) represent.

Переглянути це питання
Consider the network below. Activity durations are given in nodes.

What is earliest finish date (EFD) of activity F?

❌
❌
✅
❌
Переглянути це питання

What the earliest start of activity G for the following network diagram? (FF-5 means Finish to Finish with -5 days lead time.)

0%
0%
0%
0%
Переглянути це питання

Briefly explain in what situation Line of Balance can be used? (in about 80 words)

Переглянути це питання

Consider the network below. Activity durations are given in nodes.

What is total float of activity D?

✅
❌
❌
❌
Переглянути це питання

What is resource leveling? What are the impacts of resource leveling on project schedule? (in about 150 words)

Переглянути це питання

50 similar houses are to be built in a housing project. For each house, 9 trade activities need to be carried out, and their relationships are given in the following network diagram. The duration of each trade activity for one house is listed in the table.

Assume all the trade activities need to be carried out continuously and the total project needs to be finished in the shortest possible time.

(1) Calculate the total duration, staring week and finishing week for each trade.

(2) Determine the total project duration.

Q7 LOB 2018 supp exam

Переглянути це питання