You have a cell suspension for which you need to determine the concentration of cells/ml. You take 20 μl of cell suspension and this with 60 μl of counting solution. You perform a haemocytometer count, and you have counted 62, 72, 61, and 68 cells in the four large outer squares (A, B, C, and D) of the haemocytometer.
What is the concentration (in cells/ml) of your sample? (Answer in standard notation (e.g. 62000 instead of 6.2 × 104).)
Based on this practical exercise, for the following conditions indicate if you would expect a high level of cell killing, an intermediate level of cell killing, or no cell killing.
The following precedence diagram shows all the activities involved in a housing project. For each activity, the most likely activity duration, the most optimistic and most pessimistic time have been given in the table (in weeks).
(1) Calculate the probability that the project can be completed in 21 weeks. Choose from answers (a, b, c, d)
(2) Calculate the probability that the project can be completed in 22 weeks. Choose from answers (e, f, g, h)
(3) If we want to be 90% sure that the project will be completed on time, how long we should schedule it? Choose from answers (i, j, k, l)
The following precedence diagram shows all the activities involved in a housing project. For each activity, the most likely activity duration, the most optimistic and most pessimistic time have been given in the table (in weeks).
(1) Calculate the probability that the project can be completed in 26 weeks. Choose from answers (a, b, c, d)
(2) If we want to be 90% sure that the project will be completed on time, how long we should schedule it? Choose from answers (e, f, g, h)
(3) If we want to be 95% sure that the project will be completed on time, how long we should schedule it? Choose from answers (i, j, k, l)