Under NZS3910:2023, what is the main focus of Contractor-arranged Plant Insurance?
To insure the Contractor’s plant and equipment used on-site.
✅
To insure only the Principal’s equipment.
❌
To provide additional liability coverage for the Contractor.
❌
To cover the costs of hiring new plant.
❌
Переглянути це питання
Under NZS3910:2023, what is the Final Payment Schedule?
The schedule for retentions only.
❌
The document detailing the final amounts payable, including adjustments.
✅
The timetable for project meetings.
❌
A preliminary estimate of costs.
❌
Переглянути це питання
Under NZS3910:2023, what is the purpose of sub‐chapter 2.7 "Evidence of Contract"?
To establish that the tender or offer together with its acceptance and related documents form the binding Contract before the Contract Agreement is executed.
✅
To provide guidelines for dispute resolution.
❌
To allow verbal agreements to form the Contract.
❌
To detail the calculation of the Contract Price.
❌
Переглянути це питання
Under NZS3910:2023, what is the role of mediation in dispute resolution?
To impose a binding decision on both parties.
❌
To serve as the final step in resolving disputes.
❌
To automatically adjust the Contract Price.
❌
To provide a non-binding, structured process for the parties to reach a mutually acceptable solution.
✅
Переглянути це питання
Under NZS3910:2023, what is the primary requirement for the service of notices?
Notices must be served in writing, using acceptable methods (e.g. registered post or email) as specified in the Contract.
✅
Notices must only be served by the Engineer.
❌
Notices can be given verbally at any time.
❌
Notices are optional and may be informal.
❌
Переглянути це питання
Under NZS3910:2023, what is the significance of sub‐chapter 5.13 "Programme"?
It sets out the design responsibilities.
❌
It details the Contractor’s payment schedule.
❌
It establishes the scheduled timeline for completing the works.
✅
It explains the method for serving notices.
❌
Переглянути це питання
Under NZS3910:2023, what does Contractor-arranged Construction Insurance cover?
It covers losses due to market fluctuations.
❌
It covers damage to the construction works during execution.
✅
It guarantees profit for the Contractor.
❌
It is optional and not mandated by the Contract.
❌
Переглянути це питання
Under NZS3910:2023, what does the variations clause permit?
It requires the Contractor to change works unilaterally.
❌
It limits variations to cost adjustments only.
❌
It allows for changes to the works instructed under the Contract.
✅
It prohibits any changes once the Contract is signed.
❌
Переглянути це питання
Under NZS3910:2023, what does the Commencement clause specify?
The date when the Contract is signed.
❌
The date when the project is handed over.
❌
The date when final payment is made.
❌
The date when the Contractor is authorised to start the works.
✅
Переглянути це питання
Under NZS3910:2023, what does sub‐chapter 5.7 "Care of the Contract Works and Site" require?
That the Contractor must maintain and protect the works and site until completion.
✅
That care of the site is optional.
❌
That only temporary works are maintained.
❌
That the Principal is responsible for site maintenance.
❌
Переглянути це питання
Попередня
1
Більше сторінок
712
713
714
715
716
Більше сторінок
144506
Наступна
Telegram
Instagram
TikTok
Question Bank
Умови використання
Зв'яжіться з нами
Додати до Chrome