The primary outputs of the Monitor-Stakeholder-Engagement process are the project work performance data/information/reports, change requests, resource management plan, communications management plan, stakeholders engagement plan, issue log, lessons learned register, risk register, and stakeholder register.
0%
0%
View this question
The Acquire-Resources process involves obtaining the project team, facilities, equipment, materials, and supplies necessary to complete the project Work.
100%
0%
View this question
The Manage-Stakeholder-Engagement process involves communicating with stakeholders to meet their expectations, address their issues, and foster appropriate stakeholder involvement.
0%
0%
View this question
The primary inputs to the Plan-Scope-Management process are the project charter, project management plan, relevant organizational process assets, and enterprise environmental factors.
0%
0%
View this question
The primary inputs to the Plan-Resource-Management process include the following:
100%
0%
0%
0%
View this question
The primary data analysis methods used during the Identify-Risks process are root-cause, assumption-and-constraint, SWOT, and document analysis.
100%
0%
View this question
The Manage-Communications process ensures effective and timely collection, creation, distribution, storage, retrieval, management, monitoring, and disposition of the project information.
100%
0%
View this question
A virtual team is a group of people with a shared goal to fulfill their roles with little or no time spent on meeting face to face. Virtual teams make it possible to establish a team without its members being in the same place.
100%
0%
View this question
The primary data analysis methods used during the Control-Schedule process include the following:
0%
0%
0%
100%
View this question
The precedence diagramming method (PDM) constructs a schedule model in which activities are represented by nodes and interlinked graphically by logical relationships to show the sequence in which they are performed.
100%
0%
View this question