logo

Crowdly

ENG4801 - Professional practice (Curriculum embedded) - MUM S1 2025

Looking for ENG4801 - Professional practice (Curriculum embedded) - MUM S1 2025 test answers and solutions? Browse our comprehensive collection of verified answers for ENG4801 - Professional practice (Curriculum embedded) - MUM S1 2025 at learning.monash.edu.

Get instant access to accurate answers and detailed explanations for your course questions. Our community-driven platform helps students succeed!

Which of the following statements are true regarding the application of a Work Breakdown Structure (WBS) in project planning? Select all that apply

View this question

Which of the following statements are true regarding resource levelling in project planning and control? (Select all that apply)

View this question

Considering

a hypothetical project's Earned Value Management (EVM) report, what does a Cost

Performance Index (CPI) of 1.07 indicate?

View this question

Which of

the following project management processes is most crucial for managing the

interdependencies between the three parallel paths in this case study?

0%
0%
0%
View this question

In project

monitoring, what does a Schedule Performance Index (SPI) of 0.9 indicate?

View this question

What is the cumulative schedule variance? (include

sign)

View this question

Based on EVM and triple constraint criteria, what factor is the most concerning

at this stage?

View this question

What is the overall project CPI value? (input numerical value up to 2 decimal

places)

View this question

You are required to report to the relevant stakeholders on

the project progress 18 weeks into the project. Below is the current progress

at the end of Week 18. Conduct the EVM analysis and answer the questions below.

Activity

% Complete

Actual Cost (RM)

A

100%

60,000

B

100%

45,000

C

100%

85,000

D

100%

85,000

E

100%

125,000

F

80%

130,000

G

100%

75,000

H

60%

120,000

I

0%

0

J

25%

60,000

K

0%

0

L

0%

0

M

0%

0

Which activity is currently behind the planned schedule the

most?

View this question

If activity E is delayed by 5 weeks from its initial schedule, what would

be the impact to its successor’s activity and overall project, assuming the rest of the activities are not experiencing any delay.

View this question

Want instant access to all verified answers on learning.monash.edu?

Get Unlimited Answers To Exam Questions - Install Crowdly Extension Now!