By which day Activity D will be finished?
Prepare a LOB schedule for the construction of 40 typical floors of a high-rise commercial building. A precedence schedule showing the sequence of a typical floor construction is given in the below Figure. Each activity will be performed by one crew of subcontractors. Durations are in days. Add time buffer zone of zero between activities.
An overlapping network diagram is given below. What is the project duration?
An overlapping network diagram is given below, what is the Early Start Date of Activity C?
An overlapping network diagram is given below. What is the Early Finish Date of Activity E?
Consider the network below. Activity durations are given in nodes.
What is earliest start date (ESD) of activity E?
What is earliest finish date (EFD) of activity G?
Consider the network below. Activity durations are given in nodes.
What is earliest start date (ESD) of activity E?
An overlapping network diagram is given below, what is the Early Start Date of Activity D?
What is earliest start date (ESD) of activity E?
What is earliest finish date (EFD) of activity F?