When an

organisation starts using forklifts or other handling equipment to replace

manual labour (the workforce), transportation time from the manufacturing plant to the warehouse decreases, which

saves costs and time.

100%
0%
View this question

The

definition “Work measurement technique

being

a development of estimating in which the time required to carry out elements of

a task at a defined rate of working is estimated partially based on the

knowledge and practical experience of the work concerned and partially from

synthetic data” refers to which one of

the following options?

0%
0%
0%
0%
View this question

Labour control

As the head of the

work study department at ABC Caps Design Company, you have been requested by

management to determine labour performances as part of a work study

investigation. The following information is available:

Number of operators

4

Attendance time (each operator)

8 hours

Type-A caps

120

Standard time per piece for A caps

10 std mins

Type-B caps

50

Estimated standard time for B caps

5 std mins

Total time spent on non-productive, uncontrolled work (group)

2 hours

Waiting and diverted time (department responsible)

3 hours

Waiting and diverted time (department not responsible)

1 hour

Use the above information

to calculate operator performance at ABC Caps.  Then state which ONE of the following is the

correct answer?

50%
50%
0%
0%
View this question

Rated activity sampling

Moloto Beverage

Company’s output during a 0.1-minute interval was 10 units of soft drink. (See

the number items and the results of elements in

Table 1 below.)

 Table 1:

Results

of the rated activity sampling study

Observation number

(0.1-min. intervals)

Worker

Element 1

Element 2

Idle

1

90

 

 

2

 

95

 

3

95

 

 

4

 

90

 

5

90

 

 

6

 

 

100

7

85

 

 

8

95

 

 

9

 

100

 

10

 

 

100

Total

455

285

200

Use the information in the table above to calculate total

basic time. Then state which

ONE

of the following options is the correct

answer?

 

0%
0%
0%
100%
View this question

Activity sampling

The study of a

single machine presented the following results after 95 random observations for

packaging were recorded to determine machine idle time and machine running

time.

Machine

No. of observations

Working

(Machine running)

Idle

A

95

75

20

%

100

 

 

Calculate the

machine idle observation percentage using the above table and state which

ONE

of the following options is the correct

answer?

0%
0%
0%
100%
View this question

When

work activities in the plant or factory are done partly manually, with the

support of the machines or equipment, the activities are categorised as____________work.

100%
0%
0%
0%
View this question

ABC Caps

produced 220 000 caps with a value of R125 per cap in 2024. The company

employed four workers at a cost of R80 000 in 2024. In 2025, the company

increased its output to 280 000 with a value of R130 per cap. The company

employed five workers at a cost of R90 000 in 2025.

Calculate the productivity index and state which

ONE

of the following options is the correct

productivity index for ABC Caps?

Calculate the productivity index and state which

ONE

of the following options is the correct

productivity index for ABC Caps?

B)     2025 = 6% decrease in

productivity

C)     2025 = 7% increase in

productivity

D)     2025 = 7% decrease in productivity

ANSWER: B

ANSWER: B

 

0%
100%
0%
0%
View this question

Let’s

say the Mathebula Brick making construction Company generates 300 000 bricks

with a value of R20 per brick using 4 workers at a cost of R90 000 for

2023

and increased output to R400 000 with a

value of R22 per brick using similar number of workers @ R110 000 for

2024.

You are

required to calculate the productivity factor and then state which

ONE

of the following option is the correct answer

for 2023?

0%
100%
0%
0%
View this question

Let’s

say the Mathebula Brick making construction Company generates 300 000 bricks

with a value of R20 per brick using 4 workers at a cost of R90 000 for

2023

and increased output to R400 000 with a

value of R22 per brick using similar number of workers @ R110 000 for

2024.

You are required to calculate the productivity

factor and then state which

ONE

of the

following option is the correct answer for 2024?

0%
0%
0%
100%
View this question

One of

the aims of measuring productivity in an organisation is to

provide a psychological stimulus____________

0%
0%
0%
0%
View this question