For a pair of activities, I and J, the succeeding activity, J, cannot be complet...

✅ The verified answer to this question is available below. Our community-reviewed solutions help you understand the material better.

For a pair of activities, I and J, the succeeding activity, J, cannot be completed until its preceding activity, I, has been fully accomplished. Such a link between activities I and J is referred to as the _____ link.
0%
50%
0%
50%