The following precedence diagram shows all the activities involved in a housing ...

✅ The verified answer to this question is available below. Our community-reviewed solutions help you understand the material better.

The following precedence diagram shows all the activities involved in a housing project. For each activity, the most likely activity duration, the most optimistic and most pessimistic time have been given in the table (in weeks).

(1) Calculate the probability that the project can be completed in 26 weeks. Choose from answers (a, b, c, d)

(2) If we want to be 90% sure that the project will be completed on time, how long we should schedule it? Choose from answers (e, f, g, h)

 (3) If we want to be 95% sure that the project will be completed on time, how long we should schedule it? Choose from answers (i, j, k, l)