logo

Crowdly

Browser

Add to Chrome

Standard deviation and variance of activities in a project are given in table be...

✅ The verified answer to this question is available below. Our community-reviewed solutions help you understand the material better.

Standard deviation and variance of activities in a project are given in table below. What is the probability (z) that the project will be completed within 23 weeks? The project duration has been calculated as 19.7 weeks. Activities A, D, and G are critical.

0%
0%
0%
100%
More questions like this

Want instant access to all verified answers on moodle.telt.unsw.edu.au?

Get Unlimited Answers To Exam Questions - Install Crowdly Extension Now!

Browser

Add to Chrome