In assigning a value for the most pessimistic ( b ) duration, the project manage...
✅ The verified answer to this question is available below. Our community-reviewed solutions help you understand the material better.
In assigning a value for the most pessimistic (b) duration, the project manager should estimate the duration of the activity to have a 99% likelihood that it will take b or less amount of time.