According to the AoN diagram as per the table, identify the LF for activity E and the EF for activity F, respectively:
Activity
|
Duration
|
Immediate follower
|
A
|
1
|
B, C, D, E
|
B
|
3
|
F
|
C
|
4
|
F
|
D
|
2
|
F
|
E
|
4
|
F
|
F
|
4
|
G
|
G
|
1
|
-
|