✅ The verified answer to this question is available below. Our community-reviewed solutions help you understand the material better.
During a 42-hour week, an embroidery machine was idle for 2 hours and broken for 2.5 hours. About 140 embroideries were produced. The standard time per embroidery is 20 minutes. Calculate the machine utilisation index (MUI). Which