logo

Crowdly

Browser

Додати до Chrome

BLDG2023-Construction Planning (T1, 2025)

Шукаєте відповіді та рішення тестів для BLDG2023-Construction Planning (T1, 2025)? Перегляньте нашу велику колекцію перевірених відповідей для BLDG2023-Construction Planning (T1, 2025) в moodle.telt.unsw.edu.au.

Отримайте миттєвий доступ до точних відповідей та детальних пояснень для питань вашого курсу. Наша платформа, створена спільнотою, допомагає студентам досягати успіху!

The following precedence diagram shows all the activities involved in the construction of one floor of a high-rise building. The duration of each activity is also given (in days).  There are 18 typical floors to be constructed for this high-rise building.

When Should Activity C Start?

0%
0%
0%
0%
0%
Переглянути це питання

For the given overlapping network diagram:

(1) Describe the relationship between all activities.

(2) Calculate the Early Start Date and Early Finish Date of each activity.

(3) Determine the project duration.

Q4 - Final Exam 2019

Переглянути це питання
Consider the network below. Activity durations are given in nodes.

What is finish time of the project?

0%
0%
0%
0%
Переглянути це питання

See below for a project's precedence diagram and each activity's duration given in the table. 

(1) If the project manager for the following project wants to be at least 80% sure about the scheduled completion time, how many weeks the project should be scheduled?

(2) What is the possibility that the project will complete in less than 32 weeks?

Q8 2019 final exam BLDG2023

Переглянути це питання
Consider the network below. Activity durations are given in nodes.

What is earliest finish date of activity F?

0%
0%
0%
100%
Переглянути це питання

An overlapping network diagram is given below, what is the Early Start Date of Activity C? 

Overlapping Network Forward Pass Extra Question 1

0%
0%
0%
0%
0%
Переглянути це питання

30 similar houses are to be built in a housing project. For each house, 10 trade activities need to be carried out, and their relationships are given in the following network diagram. The duration of each trade activity for one house is listed in the table. 

Assume all the trade activities need to be carried out continuously and the total project needs to be finished in the shortest possible time.

(1) Calculate the total duration, starting week and finishing week for each trade using the LOB method.

(2) Determine the total project duration.

Q7 LOB 2019 Final Exam

Переглянути це питання
Consider the network below. Activity durations are given in nodes.

What is latest start date (LSD) of activity E?

0%
0%
0%
0%
Переглянути це питання

Explain what are time schedule, resource schedule and target schedule? (in about 120 words)

Переглянути це питання

For the given overlapping network diagram:

(1) Describe the relationship between all activities. (For example, AC is Finish to Finish).

(2) Calculate the Early Start Date and Early Finish Date of each activity.

(3) Determine the project duration.

Q4 - CONS0009 Supp exam 2018

Переглянути це питання

Хочете миттєвий доступ до всіх перевірених відповідей на moodle.telt.unsw.edu.au?

Отримайте необмежений доступ до відповідей на екзаменаційні питання - встановіть розширення Crowdly зараз!

Browser

Додати до Chrome