logo

Crowdly

Browser

Додати до Chrome

BLDG2023-Construction Planning (T1, 2025)

Шукаєте відповіді та рішення тестів для BLDG2023-Construction Planning (T1, 2025)? Перегляньте нашу велику колекцію перевірених відповідей для BLDG2023-Construction Planning (T1, 2025) в moodle.telt.unsw.edu.au.

Отримайте миттєвий доступ до точних відповідей та детальних пояснень для питань вашого курсу. Наша платформа, створена спільнотою, допомагає студентам досягати успіху!

An overlapping network diagram is given below. What is the Early Finish Date of Activity E? 

ONM forward pass Extra Q1

Переглянути це питання

You have a project to be completed in 6 months. At the third month, project team members report that it is 45% complete. The planned budgeted cost at the third month was $250,000. You have spent $232,000 of the project's $500,000 budget. What is the PV, AC, BAC, EV, CV, CPI, SV, SPI, ETC and EAC at the day of reporting the project status? 

Comment on the results and explain briefly what the value of each item means for the project.

( PV: Planned Value;  AC: Actual Cost; BAC: Budget At Completion; EV: Earned Value; CV: Cost Variance; SV: Schedule Variance; CPI: Cost Performance Index; SPI: Schedule Performance Index; ETC: Estimate To Completion; EAC: Estimate At Completion )

 

Переглянути це питання

All of the following statements are true EXCEPT:

Переглянути це питання

Explain in what situation PERT analysis may underestimate schedule risk, and in what situation PERT can be more accurate in predicting schedule risk? (in about 100 words)

Переглянути це питання

See below for a project's precedence diagram and each activity's duration given in the table. 

(1) If the project manager for the following project wants to be at least 90% sure about the scheduled completion time, how many weeks the project should be scheduled?

(2) What is the possibility that the project will take longer than 33 weeks?

Q8 2019 final exam BLDG2023

Переглянути це питання
Based on the following network diagram, what is the duration of the critical path? (FF+2 means Finish to Finish with 2 days lead time.)

0%
0%
0%
0%
Переглянути це питання
Consider the network below. Activity durations are given in nodes.

What is earliest finish date (EFD) of activity F?

Переглянути це питання

What the earliest start of activity G for the following network diagram? (FF-5 means Finish to Finish with -5 days lead time.)

0%
0%
0%
0%
Переглянути це питання

Briefly explain in what situation Line of Balance can be used? (in about 80 words)

Переглянути це питання

Consider the network below. Activity durations are given in nodes.

What is total float of activity D?

Переглянути це питання

Хочете миттєвий доступ до всіх перевірених відповідей на moodle.telt.unsw.edu.au?

Отримайте необмежений доступ до відповідей на екзаменаційні питання - встановіть розширення Crowdly зараз!

Browser

Додати до Chrome