Assuming that lowest bidder wins at the lowest bid price, your firm’s cost esti...

✅ Перевірена відповідь на це питання доступна нижче. Наші рішення, перевірені спільнотою, допомагають краще зрозуміти матеріал.

Assuming that lowest bidder wins at the lowest bid price, your firm’s cost estimates and bids, and bids of its competitors for the last five construction contracts are as below. (Show all calculations, 22%)

 

Contract

Your firm cost estimates (mil)

Your firm bids (mil)

Competitor A bids (mil)

Competitor B bids (mil)

Competitor C bids (mil)

1

210

222

235

215

240

2

115

130

128

132

131

3

55

60

57

58

55

4

110

110

118

121

123

5

385

395

388

387

390

 

 

(a)  What is the average percentage mark-up of your firm for the five bidding attempts? (5%)

(b)  For the five bidding attempts, evaluate the bidding performance (i.e., bidding competitiveness and consistency in bidding) of your firm using the Bid Competitiveness Ratio (BCR) measure. (10%)

(c)   Make two comments on the results obtained in (b). (3%)

(d)  Calculate the market share of your firm and its competitors, comment on the results. (4%)

Більше питань подібних до цього

Хочете миттєвий доступ до всіх перевірених відповідей на moodle.telt.unsw.edu.au?

Отримайте необмежений доступ до відповідей на екзаменаційні питання - встановіть розширення Crowdly зараз!

Browser

Додати до Chrome