You are required to report to the relevant stakeholders on

the project progress 18 weeks into the project. Below is the current progress

at the end of Week 18. Conduct the EVM analysis and answer the questions below.

Activity

% Complete

Actual Cost (RM)

A

100%

60,000

B

100%

45,000

C

100%

85,000

D

100%

85,000

E

100%

125,000

F

80%

130,000

G

100%

75,000

H

60%

120,000

I

0%

0

J

25%

60,000

K

0%

0

L

0%

0

M

0%

0

Which activity is currently behind the planned schedule the

most?

❌
❌
❌
✅
View this question

What is the free float value for activity J? 

View this question

If activity E is delayed by 5 weeks from its initial schedule, what would

be the impact to its successor’s activity and overall project, assuming the rest of the activities are not experiencing any delay.

0%
0%
0%
0%
0%
View this question

If activity J is experiencing 7-week delay compared to its initial schedule, what would be the impact to its successor activity and overall project? Assume the other activities are on-track.

❌
❌
✅
❌
View this question

Identify the ES for activity K (insert numerical value)

View this question
Identify the LF for activity J (insert numerical value)
View this question

Based on the case study above, identify the project's critical path

0%
0%
0%
0%
0%
View this question

Identify the LS for activity L (insert numerical value)

View this question

Based on your network diagram, identify the LS of activity E (insert numerical value)

View this question

The Advanced Rural Water & Energy

Sustainability Project

An

engineering consortium that you work for is tasked with a comprehensive project

in a remote rural region, focusing on water purification, renewable energy, and

sustainable waste management. The project aims to provide clean water, reliable

energy, and improve sanitation. You are assigned as the project manager to

oversee the project’s progress. Based on the stakeholder’s engagement and

previous projects, you have estimated the relevant costs, duration as well

interdependencies of each activity as summarised in the table below.

 

Activity

Description

 Predecessor(s) 

 Duration (Weeks) 

 Planned Cost (RM)

A

Community Needs & Site Assessment

-

4

60,000

B

Water Source Analysis & Testing

A

3

40,000

C

Solar Panel System Design

A

5

80,000

D

Water Purification System Design

B

6

90,000

E

Solar Panel Procurement & Delivery

C

4

120,000

F

Purification System Procurement

D

5

150,000

G

Biogas Digester Design

A

4

70,000

H

Solar Panel System Installation

E

7

180,000

I

Water Purification System Installation

F

6

160,000

J

Biogas Digester Construction

G

8

200,000

K

Integrated System Wiring & Control

H, I, J

5

100,000

L

Water & Energy Quality Validation

K

3

60,000

M

Community Training & Handover

L

4

80,000

 

Prepare a network diagram and answer the following questions.

What is the total duration of the project (in weeks). Insert

numeric value in the box below

View this question