logo

Crowdly

Browser

Add to Chrome

MNO3701-26-S1

Looking for MNO3701-26-S1 test answers and solutions? Browse our comprehensive collection of verified answers for MNO3701-26-S1 at mymodules.dtls.unisa.ac.za.

Get instant access to accurate answers and detailed explanations for your course questions. Our community-driven platform helps students succeed!

Which statement is correct

?

View this question

Which

of the following is

NOT a cost associated with quality?

a     Opportunity

cost

b     Prevention

cost

c     Appraisal

cost

d    Internal

failure cost

e    External failure cost

View this question

The

inventory record (item master file) shows the following planning factors:

batches are set at quantities of 25, safety stock is set at 5 handles, the

available inventory is 90 and the lead time for orders is 2 weeks. When will

the

first and second orders be issued?

View this question

Material

requirements planning (MRP) is used to plan and control material requirements.

The master production schedule (MPS) for three sizes of the screwdriver is

given in the table. All three screwdrivers (2 mm, 7 mm and Star 5)

use the same handle. The available stock is 70, orders are placed in batches of

20 and the safety stock is set at 2. Lead time is 2 weeks.

Item

Week

1

2

3

4

5

2 mm

10

 

 

10

 

7 mm

18

 

18

 

18

Star

5

8

8

8

8

8

MPS

36

8

26

18

26

In

which week is the

second planned order?

View this question

Which option is incorrect

regarding TQM?

View this question

Which

of the following can be defined as a project?

a     Designing

an aircraft

b     Producing

a television programme

c     Refurbishing

of a hotel

d     Planning,

organising and running a major international sports event

e    A set of activities with a

defined start point and a defined end state, which pursues 

a defined goal and uses a defined set of

resources

View this question

According

to the AoN diagram as per the table, identify the LF for activity E and the EF

for activity F, respectively:

Activity

Duration

Immediate follower

A

1

B, C, D, E

B

3

F

C

4

F

D

2

F

E

4

F

F

4

G

G

1

-

 

View this question

Which

of the following are typical problems experienced during the implementation of the

enterprise resource planning (ERP)?

a     The level of outside

expertise required will be more than anticipated.

b     The total cost is likely to

be underestimated.

c     The changes required to

business processes will be greater than expected.

d     There will never be enough

training.

e     Controlling the scope of the

project will be more difficult than expected.

View this question

Activity

Duration

Immediate follower

A

1

B, C, D, E

B

3

F

C

4

F

D

2

F

E

4

F

F

4

G

G

1

-

 

From

the AoN in question 1 (above) , identify the activity (activities) with slack:

a     Activity A

b     Activity B

c     Activity C

d     Activity D

e     Activity E

View this question

Which option

regarding operational TQM is

correct?

View this question

Want instant access to all verified answers on mymodules.dtls.unisa.ac.za?

Get Unlimited Answers To Exam Questions - Install Crowdly Extension Now!

Browser

Add to Chrome